|
|
"Pendleton wind project hits
snags"
by Jim
Balow, staff writer
December 10, 2004 The Charleston Gazette
A proposed $100 million wind energy
project in Pendleton County faces two potential roadblocks one
from the county commission, one from state regulators.
After a tumultuous meeting Tuesday at which county residents protested
a November deal under which county commissioners could obtain power line
easements by eminent domain, commissioners agreed to cancel their contract
with Liberty Gap Wind Force LLC. They plan to do so in a special meeting
today. Commissioner Joe Bodkin Jr. said the commissioners signed a termination
agreement Wednesday the same day they were sued for allegedly violating
open meetings laws in connection with their role in signing the original
contract. Its been rescinded, as of yesterday morning,
Bodkin said Thursday. We saw a lot of difficulties. Bodkin
said the cancellation agreement was signed and faxed by the president
of US Wind Force, parent of Liberty Gap, through a conference call. Were
just having a meeting tomorrow to confirm it.
Lawyer Zelene Harman, who filed the suit, said she would withdraw it if
and when the commission cancels its eminent domain contract.
Jim Cookman, spokesman for Liberty Gap, confirmed the contract will be
canceled. It puts us back at square one. We still desire very
much to move forward with the project, he said. We continue
to desire to work with county officials, to understand their wants and
needs in being a good corporate citizen. This is all about the transmission
line. To some its about the project itself, but to me its
the eminent domain issue and the expediency. He heard the concerned
citizens loud and clear.
We need to negotiate with the property owners to find a way to transport
the electrons to the grid. County officials will no longer negotiate
for easements, he said. It will be us, US Wind Force. Meanwhile,
staff of the state Public Service Commission has recommended the PSC move
slowly in deciding whether to grant a required state permit for the project.
Liberty Gap officials had asked for expedited treatment for their request
to build up to 50 electricity generating wind turbines on Jack Mountain,
about 10 miles south of Franklin. The company said in order to complete
the project by the end of 2005 to qualify for needed federal production
tax credits, it would need PSC approval no later than March 1, 2005. Instead,
in a joint memo written Tuesday, PSC staff recommends the PSC take 270
days or roughly nine months to consider the application. That would delay
a decision until about mid-August, and probably make it difficult for
the company to build the project by the end of 2005. In the memo explaining
the reasons for denying the companys request, PSC staff attorney
Leslie Anderson writes, First and foremost, the Legal Division notes
that this application did not contain the detailed information needed
before the staff can fully conduct its investigation.
Also Tuesday, Anderson sent Liberty Gap officials a list of detailed questions
from PSC staff items not included in the original Nov. 18 application.
It includes requests for a project schedule, site analysis information,
detailed maps, layout and construction data, financial data including
the expected effect of the production tax credits, environmental data,
and noise and cultural impacts.
Some of the requested information is similar to requirements in a set
of proposed siting rules for wind power projects the PSC has drafted but
not yet adopted, Anderson said. Weve taken into consideration
things weve learned from past cases, she said. Anderson gave
Liberty Gap until Dec. 27 to answer the staff requests. In her staff memo,
she notes, If Liberty Gap is unable to supply most of the information
requested in a timely manner, then staff may file a motion requesting
that these applications filed by Liberty Gap be dismissed until such time
as Liberty Gap has sufficient time to refile the applications. The
commission should not be short-changed simply because the applicant was
not fully prepared when making its initial filing.
Cookman said the company will deal with the PSC rulings as best it can.
Were not going to go away. We have every intent to comply.
The slower timetable may delay completion of the project, he said. It
becomes a 2006 or 2007 project, but well deal with it in a proper
business and legal manner. In Pendleton County, Bodkin said commissioners
decided to change their position after their meeting Tuesday morning.
We had a lot of people come in and protest.
Mike Roberts, a lawyer from Moyers, said he was among the 90 or so people
who attended that meeting. Of course they moved out of the commission
room into the courtroom, he said. If that meeting were held
today, there would not be a venue in the county large enough to hold everyone.
Other than the principals involved, only one other person was in
favor, of the project. Everyone else was opposed, for various
reasons. A lot of people felt eminent domain was improper, to benefit
a private enterprise. There are many good things about wind energy,
but you wouldnt put it on the mall in Washington, you wouldnt
put it in Jackson Hole, Wyoming, which has lots of wind, or in Yellowstone
National Park. You shouldnt put it in Pendleton County.
Bodkin acknowledged county officials kept word of the project quiet. I
think we did keep it a little low key. That was probably the wrong approach,
in hindsight. We were just trying to get some industry into the county,
some revenue. All we were trying to do was get the transmission
line right of way. We didnt see a lot of problem.
Roberts said he and his wife,
Paulette, first learned about the project after the weekly Pendleton Times
printed a story last week about the project, after the county commission
had signed its contract with Liberty Gap. Weve been sick for
about a week, Paulette Roberts said. People are upset
about the project but outraged about the process.
Robbie Sites, who organized a community group called Friends of Beautiful
Pendleton County, said a public meeting is scheduled at 7 p.m. Monday
in the Pendleton County High School gymnasium. The groups Web site
is www.hushhushrushrush.com.
US Wind Force has a brochure about the project on its Web page, uswindforce.com.
Go to Projects, then Liberty Gap, and click on brochure. Some
of the economic benefits promised in the brochure will become outdated
once the county commission cancels its contract, Cookman said.
|
|